Jeernodhara

Shilpi's Workshop Visit

After one month i.e. on 29/09/2023 the Core Committee members made site visit to Sri Nagraj Tantri’s work shop and are happy to observe that 30% of sculpture work is already finished. Besides Sri Tantri has assured that by Diwali festival he will finish 65% of sculpture work and the finished sculpture granite loads will be shifted to temple. According to him within 4 month’s time, after laying foundation stone, he will finish granite construction work up to roof level. Thereafter copper roof work will commence.

The Core Committee is currently working on selection of suitable Carpenter and augmentation of required good quality wood.